Perak Infrastructure, Energy, Water and Public Transportation Committee chairman Datuk Seri Mohammad Nizar Jamaluddin said the RM450 million Sungai Kinta flood mitigation project must be resubmitted in 2027 for implementation from 2028. — B

Perak Infrastructure, Energy, Water and Public Transportation Committee chairman Datuk Seri Mohammad Nizar Jamaluddin said the RM450 million Sungai Kinta flood mitigation project must be resubmitted in 2027 for implementation from 2028. — Bernama pic

First Published: Tuesday, 24 Nov 2026 11:01 AM MYT

Last Modified: Tuesday, 24 Nov 2026 11:03 AM MYT

IPOH, Nov 24 — The proposal for the Phase 3 Sungai Kinta Flood Mitigation Plan (RTB) project, valued at RM450 million under the 13th Malaysia Plan (MP13), must be resubmitted in early 2027 for implementation starting from Rolling Plan 3 (RP3) in 2028, in accordance with new guidelines from the Ministry of Economy.

State Infrastructure, Energy, Water, and Public Transportation Committee chairman Datuk Seri Mohammad Nizar Jamaluddin said this move follows the requirements set out in the guidelines for the preparation of the 13th Malaysia Plan (13MP), which mandate that high-value projects exceeding RM300 million must be submitted well in advance.

“The application for the project in question was submitted to the Flood Management Division (BPB) of the Department of Irrigation and Drainage (JPS) Malaysia on December 15, 2025. It entails a cost of RM450 million and encompasses the entire Kinta River basin, including Sungai Kampar and Sungai Keranji in the Kampar District.

“This application covers a list of projects for implementation over a five-year period ending in 2030. Should a ministry or department fail to submit an application within the stipulated timeframe, they may do so subsequently in March 2027, for project implementation beginning with the Third Rolling Plan (RP3) of 2028 under 13MP,” he said.

He said this during the oral question-and-answer session at the State Legislative Assembly sitting held at Perak Darul Ridzuan Building here today.

Mohammad Nizar was responding to a question from Koo Haai Yen (PH-Keranji), who sought an update on the status of the proposed Phase 3 Flood Mitigation Plan for the Sungai Pinji and Sungai Kinta, a project that also includes Sungai Kampar and Sungai Keranji.

Elaborating further, Mohammad Nizar noted that while awaiting the realization of these large-scale flood mitigation projects, JPS has identified several locations along Sungai Keranji suffering from bank erosion that require urgent repair. Priority is being given to areas of public interest, those deemed critical, and based on the allocations received.

“Regarding routine maintenance, JPS has spent a total of RM1,117,760 between 2022 and 2026 on cleaning works, river deepening (dredging), the removal of flow obstructions, and the reinforcement and repair of riverbank structures at Kampung Orang Asli Batu Berangkai and Jalan Wah Loong.”

“In 2026, JPS also carried out restoration work on the erosion control structures along Sungai Keranji at Jalan Angkasa 5, valued at RM41,055, using emergency, unforeseen-circumstance funds. while an application for an estimated allocation of RM300,000 is being prepared for periodic maintenance of the river in 2027, subject to the approval of funds for that year,” he said.

He added that the Perak State JPS has also submitted a request for RM297 million in federal government funding under 13MP specifically for the 2027 Rolling Plan 2 to implement Phase 2 of the Flood Mitigation Project (RTB) for the Sungai Beruas Basin in the Manjung district. The scope of work includes the construction of flood embankments, river deepening and widening, flood retention ponds, pump houses, flood control gates, bridges, and crossings. — Bernama