The Hikuwai Bridge on the East Cape is finally reopening, nearly four years after Cyclone Gabrielle destroyed it.
The bridge is on State Highway 35 between Tokomaru Bay and Tolaga Bay, and was washed away in floodwaters in February 2023. It connects Gisborne and Tolaga Bay with the rest of the East Coast, including Tokomaro Bay, Ruatoria and the East Cape.
The community rallied to get a temporary detour road in place through private land owned by the Pourau Incorporation, and a few months later a one-lane Bailey bridge was installed.
Pita Cunningham owns Cafe 35 in Tokomaru Bay and is thrilled to see the bridge reopen.
"It's wonderful. It's been a long time coming but it's here now, so it's great," he said.
He lost all business for two months after the cyclone while locals rallied to get the bypass open.
"You take a big hit from those things so it takes a while to recover, but we're going to have a good summer. People hesitate over Bailey bridges and what not but it should be fine," he said.
Pourau Incorporation chair Philip Hope told RNZ it was a big moment to see the new Hikuwai Bridge completed.
"We've worked together to inform and support the cultural integrity of this bridge build, and it was really heartening the other day, we did a walk over just in final preparation, to see a school of mullet and tuna just swimming up the Hikuwai River... it was really special," Hope said.
The $50 million bridge has been designed so it can go underwater in future floods and withstand the force of debris piling against it.
Transport Rebuild East Coast project manager Richard Bayley said a lot of engineering had gone into the build.
"We've got quite a unique situation where we've got an old cliff face that's under the riverbed and on one side the silt means we've got piles 50 metres deep so the bridge is embedded in hard rock, and on the northern side they're a bit shallower.
"It's been quite challenging engineering... it's the strongest bridge built to the highest standard in our region. We're really confident this will withstand the test of time," Bayley said.
Hope and Cunningham are hoping other parts of State Highway 35 will also be upgraded.
"Resilience is still an issue on the coast - it's wonderful we are getting this bridge in and we are grateful, but there are many other bridges across our rohe that need to be replaced," Hope said.
"Roading up here has always been an issue so we just hope for a bit more love," Cunningham said.
Although both lanes of the new bridge opened on Wednesday, Bayley said it would be back to one-way traffic from Thursday so the Bailey bridge could be removed and taken to a storage facility in Hastings.
"It's time for that to come out so we need a little bit of room to operate on. Once it comes out we still have a bit of work to do on that side of the bridge below it.
"By Christmas it'll be fully open and everyone off site," he said.