Documents show Internal Affairs wrote off at least $23 million on an IT project then came up with a revised plan that turned out to be "overly aggressive" and too risky.

Having failed once, the papers show the department (DIA) then failed to put enough resources into its second attempt, and to cap it off the work to fix the second plan has itself been delayed with no end in sight, RNZ can reveal.

The Civil Registration births, deaths and marriages' system has 25-year-old unreliable technology that guards 80 million records.

RNZ first revealed how the project to give people faster and more secure access to their identity data was stopped then written off two years ago, then restarted last year. DIA became embroiled in a legal scrap with the Australian vendor.

The newly released documents now show within three months of the restart by Cabinet a year ago, independent reviewers rated the new preliminary business case "amber-red" - successful delivery in doubt with major risks in key areas that needed prompt action.

The minister was alerted and senior officials told to act.

An Action Plan to fix what was now being called "Civil Registration 2.0" within DIA was hatched in February.

But by May, that plan had not been assessed and no improved indicative business plan had been done as expected.

Instead, another review was scheduled to be done by November.

Yet again, this review has not been done. The project team is still working on the preliminary plan.

"We are still considering timing for the completion of this work," chief financial officer Jenny Livschitz told RNZ this week.

The Civil Registration project was initially heralded as a key part of the department's $300m Te Ara Manaaki project. Instead, Te Ara Manaaki is in its final stages, and Civil Registration might have to wait till it's fully finished so it can pick up some of its experienced people.

Echoes of MBIE

The Civil Registration write-off in 2024 and restart had echoes of the Ministry of Business, Innovation and Employment this year writing off $50m on a biometric project that it was now trying to revive.

The tech wrecks have kept coming despite the alarm going up in 2023 about an "unaffordable" IT wishlist of $12 billion that public agencies foresaw needing in coming years, and big efforts by the likes of all-round fixit minister Chris Bishop to impose controls and standardisation on agencies' tech projects.

Chris Bishop

Chris Bishop has tried to impose controls and standardisation on agencies' tech projects.

RNZ / Baz Macdonald

The job has only got tougher. Globally, the escalation this year of faster, sophisticated cyber attacks by AI agents is making replacing old government systems harder - for virtually anyone: "AI has transformed the Pentagon's aging networks into a national security risk," the Washington Post has reported.

Internal Affairs has no choice but press on because the Civil Registration system is indispensable to people's identity and life-event initiatives.

'Patchwork'

But at the same time the existing system is "a patchwork of disparate technologies" and "increasingly unfit for purpose", according to the reviewers.

Part of $30m in spending last year was to maintain the stability of existing system while the longer-term replacement carried on.

"This investment will reduce the risk of service failure by implementing stronger security measures and better fraud detection, increasing the overall stability and resilience of government services.

"Public and private entities will be able to securely retrieve identity data when needed, where they are authorised to do so, expanding the range and efficiency of digital offerings for all New Zealanders."

But fixing it is particularly complex as lots of other agencies get information from it.

At a select committee in 2024, Internal Affairs promised to MPs that it would deliver a new registration system that would update itself instantly.

Two years and a failed attempt later, the 'Gateway' review ordered by Treasury in January concluded, "The Indicative Business Case (IBC) is at a very early and raw state of development, requiring significant work across all cases."

Though it said the project team had made a big effort to learn from "the previous failed attempt", they fell short.

"The current plan is deemed overly aggressive, high-risk, and reliant on excessive parallel activities."

The reviewers told DIA to make eight "urgent" fixes including:

  • "Rework the financial case" to figure out the costs and funding sources.
  • Loop in the government chief digital officer "to avoid rework or unforeseen costs".
  • "Strengthen the case for change."

Department of Internal Affairs

The Department of Internal Affairs.

RNZ / Alexander Robertson

What is it costing?

Despite all the past work on version 1.0 since 2022, by January 2026 the review found "the programme costs reviewed are currently based on an early, low confidence estimate".

"At this stage, the level of uncertainty is too high for the financial case to be presented to government."

All this reviewing and reworking is costing, too.

The reviewers interviewed two dozen people and looked through scores of documents.

They were told that "interim funding" would be needed to get to the detailed business case stage, plus the project would have to allow for money to cover legislative changes that might impact it.

Emails showed the department was both relieved the plug had not been pulled entirely, and put out.

"It [the review] did not recommend we stop business case work or that there wasn't a case for investment," a memo to the Secretary of Internal Affairs said on 5 February.

"An important lesson is that we should have pushed back harder against the timing of the Gateway review" because it was too early to show they had strong approaches.

They were "heartened" reviewers found "many positives" but "overall, we agree with the gaps the review team identified".

What are they building?

It remains unclear if the project team knows what it is building.

That is certainly the case for the taxpaying public as Livschitz refused to release to RNZ an update for the public on the current scope, viability, cost and timeline of the project, on the grounds Treasury would do that "soon". No date was given for that.

Official Information Act requests have been known to be delayed this way by agencies then it taking months for the information to be "proactively released". RNZ has complained to the Ombudsman about this.

One remedy the 2.0 project team put forward in February was: "Providing better evidence for and tighter narrative of the problems with the current system and potential ways forward."