Open power lines passing through an oilpalm plantation field in Nirmal district.

Open power lines passing through an oilpalm plantation field in Nirmal district. | Photo Credit: By Arrangement

HYDERABAD

On behalf of farmers raising oilplam plantation expressing concern about overhead power transmission cables passing over their plantations, Minister for Agriculture Tummala Nageswara Rao has proposed to the State government to replace such open power lines with aerial-bunched (AB) lines.

The minister has taken up the matter along with suggestions to the notice of Chief Minister A. Revanth Reddy and Deputy Chief Minister M. Bhatti Vikramarka, who holds the Energy portfolio too. The replacement of open cables with AB lines would not only help reduce electricity-related accidents in the plantations but also help farmers get additional income by allowing them to utilise the land completely.

The move would help make oilpalm cultivation more profitable in the State, the minister said, adding that the State government had been giving high priority for extending oilpalm cultivation. He stated that the open power lines could be replaced with AB lines wherever possible technically.

Stating that the extent of oilpalm plantation had reached 3.37 lakh acres raised by about 92,000 farmers till October 2026 from 46,000 acres in 2020-21, the minister said the government was going ahead with plans to extend it to 10 lakh acres in the next few years. Besides, the government was also taking steps to provide support in the form of nurseries, drip irrigation systems, management of plantations, procurement of oilpalm bunches and increasing the processing capacity.

In 2025-26, the Telangana Oilfed had procured 4.74 lakh tonnes of oilpalm fresh fruit bunches and paid ₹1,100 crore to farmers as the proceeds. He explained that passing open power transmission lines over the oilpalm plantation fields was reducing the number of plants per acre, which would be generally 50 per acre. Even the passing of 11 kV LT lines was reducing the number of plants per acre by 8 and farmers were losing income for the lifetime of the plantation.

The problem had come to light during a field examination at Kanakapur village in Laxmanchanda mandal of Nirmal district. In the 4.5 acre oilpalm plantation of a farmer there, he could not plant about 20 plants as the 11 kV line passes from the middle of the field for 150 metres length. The loss of income from 20 oilpalm trees for their lifetime of 35 years would work out to ₹27.45 lakh at the current prices of oilpalm bunches.

However, the power utility had estimated the loss only at ₹9.82 lakh and the cost of replacing open transmission lines with AB lines was only ₹1.45 lakh. Replacement of open cables with AB lines would cost in the range of ₹61,000 to ₹76,000 per acre. The shifting of lines to the boundary of plantation was leading to new land acquisition issues, in addition to the cost of new poles and shifting charges up to ₹3 lakh.

Published - November 22, 2026 09:35 pm IST

Source: The Hindu · The Hindu Bureau

At a glance

Topic
World
Country
🇮🇳 IN
Publisher language
EN