In a major infrastructure push ahead of the Sabarimala pilgrimage season, the Public Works department (PWD) has completed the renovation of the 4.5-km Chalakkayam-Pampa road in just 30 days, spending ₹14.14 crore, authorities said.

The road, a crucial access route for pilgrims heading to the temple, was upgraded against a stipulated construction period of nine months, authorities said on Friday.

The 41-day-long Mandalam pilgrimage season will commence on November 17.

According to the district administration, the work commenced on October 13 and was completed on November 13.

Signboards, crash barriers and road markings have also been installed at vulnerable locations to enhance road safety.

The renovation was undertaken following a decision at a review meeting on Sabarimala preparations chaired by Chief Minister V.D. Satheesan, they said in a statement.

The road, which had been maintained by the Travancore Devaswom Board (TDB), was in poor condition and posed challenges during the pilgrimage season, it said.

The PWD undertook the specific renovation without taking over ownership of the road, using government funds instead of the Devaswom Board’s deposit.

District Collector A. Nizamudeen said the timely completion was the result of coordinated efforts by the district administration, PWD officials, police and the contractor.

Favourable weather conditions also helped expedite the work, he added.

Published - November 13, 2026 07:47 pm IST

Source: The Hindu · PTI