The Republic has had a poor reputation for delivering critical infrastructure projects. Delays, huge cost overruns and, in some cases, abandoning projects, have all contributed to this reputation. The Government’s Accelerating Infrastructure Taskforce was a high-level response, and its report late last year set out an ambitious action plan.

Key recommendations include legal reform, which would streamline judicial review processes, and the introduction of a Critical Infrastructure Bill to fast track vital national projects. It also proposed cutting red tape across State bodies, developing clear national planning statements for critical infrastructure, and boosting building sector productivity by expanding modern methods of construction, including use of AI. The taskforce also called for the private sector to take a bigger role in building critical water and electricity infrastructure.

Nine critical projects have been earmarked for fast-tracking, including MetroLink in Dublin, the Cork Area Commuter Rail Programme and the Galway Ring Road, as well as various water, environmental and major energy infrastructure projects throughout the State.

Progress has been rapid. Significant legislative changes have come into effect this year. The Critical Infrastructure Act passed into law in June, while the new Planning and Development Act has been in effect since July.

The Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation, Jack Chambers, recently delivered an update on the Accelerating Infrastructure Action Plan, confirming that delivery on more than 95 per cent of commitments in quarter two had been completed. The plan, which includes 30 targeted actions to address key barriers to infrastructure delivery, is already producing results, with legislative, regulatory and process reforms progressing strongly across Government, the Minister said.

Former Glen Dimplex chief executive Sean O’Driscoll, a member of the Accelerating Infrastructure Taskforce, told the annual conference of the Construction Industry Federation in late September he had been “blown away” by the progress that had been made in the first 10 months of this year. He told the conference that 77 per cent of the overall targets of the taskforce had been implemented at that point and the rest would be delivered by the first quarter of 2027.

Liam Kenny, chief executive of John Paul Construction, says the Accelerating Infrastructure Taskforce has been an important catalyst for change, helping to focus attention on some of the most significant barriers to infrastructure development in the State.

Liam Kenny, John Paul Construction CEO

Liam Kenny, John Paul Construction CEO

“The taskforce has helped drive greater co-ordination between utilities organisations and other stakeholders, while increasing the focus on digitalisation and consenting reform, all of which are critical to improving how major projects are planned and delivered,” he says. “The priority now is to build on these advances and provide greater pipeline certainty so the industry can invest with confidence and continue delivering the infrastructure Ireland needs.”

MetroLink is a good example of progress. Commitment to the project has been clear, and both the domestic and international construction market have responded positively, says Kenny. The challenge now, he says, is to replicate that certainty and ambition across a broader range of infrastructure projects. Recent progress on other initiatives such as the Greater Dublin Drainage scheme and Marine Area Consent timelines suggests things are moving in the right direction.

“Rather than creating renewed impetus, the priority should be to maintain the momentum already generated, continue delivering on the taskforce’s recommendations and provide greater pipeline certainty so the industry can invest with confidence and deliver the infrastructure Ireland needs,” says Kenny.

In the taskforce report, the Government acknowledges that the systems developed over time to underpin infrastructure development, including legal and regulatory systems, have been built with the best of intentions of protecting citizens’ rights, promoting transparency and protecting the environment. “What has been missing is consideration of the cumulative impact that each additional requirement imposes on the development of infrastructure, the risks of delay this creates, and the resulting costs that delays impose on society,” it notes.

The report adds that in many cases the delays imposed by overly strict environmental protections are likely to result in worse environmental outcomes.

Phoebe Duvall of An Taisce, however, believes curbs on planning objections will restrict the public’s ability to access justice, while the State and developers will be essentially unhindered.

Phoebe Duvall, An Taisce senior planning and environmental policy officer

Phoebe Duvall, An Taisce senior planning and environmental policy officer

“Contrary to the Government’s narrative, the actual data show that only a very small fraction of planning decisions end up in court. The key to getting the critical infrastructure we need permitted is ensuring that planning authorities are well equipped to make robust decisions efficiently, not removing safeguards at a time when our environment, which we are all completely reliant on, is already in a dire state,” she says.